Android / Impress timeline / plan ...
Michael Meeks
michael.meeks at suse.com
Fri Jul 13 05:03:58 PDT 2012
Hi Andrzej,
As agreed; the plan is to work the weeks: July 16th to end Sep 24th;
and we have the following breakdown / task ordering with time estimates.
The estimates are primarily for practising estimating things, and of
course switching things about is just fine; but it's nice to get a gauge
of how long things take :-) My view is that they are under-estimates,
but I hope to being wrong :-)
It's an exciting project for sure, and I look forward to it's
completion & using it myself.
Thanks,
Michael.
Tasks refer rather succinctly to the beautiful design from the UX team
that is here:
https://wiki.documentfoundation.org/Design/Whiteboards/Impress_remote#Tentative_Design
A. sync. issues with protocol, tracking slide changes,
protocol / priority issues => queue of requests
to process. [ 3md ]
B. Thumbnail view [ 2md ]
C. 3D slide / next-slide view [ 5md ]
D. Red bar at top + timer [ 2md ]
E. Options / blank-screen etc. [ 2md ]
F. Notes export as XHTML & rendering [ 2md ]
G. pairing / discovery / selection + PIN UI [ 5md ]
H. Error / dis-connection screen [ 1md ]
I. Rotated views [ 1md ]
J. touch navigation via volume controls [ 1md ]
K. Credits screen [ 1md ]
L. bluetooth discovery / integration [ 5md ]
M. debugging / polish / etc. - [ remainder ]
--
michael.meeks at suse.com <><, Pseudo Engineer, itinerant idiot