On Sat, Nov 04, 2006 at 01:54:48PM +0200, Daniel Stone wrote:
> On Sat, Nov 04, 2006 at 11:37:05AM +0100, Stefan Dirsch wrote:
> > On Fri, Oct 13, 2006 at 07:09:48PM -0400, Adam Jackson wrote:
> > > Due to relativistic time dilation, RC1 is happening a week later than
> > > planned. The release schedule is shifted whole by a week to compensate:
> > >
> > > RC1: October 13
> > > RC2: November 3
> >
> > Any new schedule available for RC2? Or is the answer "It's done when
> > it's done."?
>
> Apparently, the answer is 'not this weekend'.
Sound like releases are only done at weekends, so it won't be
available before November 10?
Do you know, which git branch will be used for RC2, so I'll be able to
take now something which is pretty close to RC2?
Best regards,
Stefan
Public Key available
------------------------------------------------------
Stefan Dirsch (Res. & Dev.) SUSE LINUX Products GmbH
Tel: 0911-740 53 0 Maxfeldstraße 5
FAX: 0911-740 53 479 D-90409 Nürnberg
http://www.suse.de Germany
------------------------------------------------------
More information about the xorg
mailing list